Job title: Gunyama Park Aquatic and Recreation Centre

Client: CPB Contractors

Duration: 20 Weeks

Description of project: Bulk Excavation, ground improvement, piling and stormwater works for the various pools and surrounding concourse areas.

Scope:

Site clearing and onsite stockpiling of material for classification
Compaction of the existing ground utilising Rapid Impact Compaction to prepare the surrounding pool and concourse area for screw piles.
Supply and installation of screw piles to meet challenging substrata conditions
Bulk and detailed excavation and trimming of the various pools and service trenches
Import of various fill materials for building pads, synthetic playing field, piling platforms and various other areas
Installation of various storm water pipes including HDPE and reinforced concrete pipes
Installation of a 220,000L inground storm water detention tank
Installation of temporary retaining walls

Value of Contract: $7 million

Project Period: February 2018 – June 2018

Client

CPB Contractors

Category

Earthworks, Remediation, Service Construction