Job title: Royal North Shore Health Hub

Client: Roberts Pizzarotti

Duration: 36 Weeks

Description of project: Demolition, Shoring, bulk, Structural piling and cores, installation of stormwater OSD for north Shore Health Hub building.

Scope:

Demolition of existing warehouse and tree lopping
Design and Construction of shoring system
Piling, capping beam, Shotcrete, Anchors, soil nail batters.
Bulk excavation approximately 17,000m3
Detailed excavation
FRP cores

Value of Contract: $9 million

Project Period: January 2019 – September 2019