Job title: Royal North Shore Health Hub
Client: Roberts Pizzarotti
Duration: 36 Weeks
Description of project: Demolition, Shoring, bulk, Structural piling and cores, installation of stormwater OSD for north Shore Health Hub building.
Scope:
Demolition of existing warehouse and tree lopping
Design and Construction of shoring system
Piling, capping beam, Shotcrete, Anchors, soil nail batters.
Bulk excavation approximately 17,000m3
Detailed excavation
FRP cores
Value of Contract: $9 million
Project Period: January 2019 – September 2019
Roberts Pizzarotti